Infrasound Group

 

Home
Windless Bight, Ant.
Fairbanks, AK
Palmer, Ant.

UAF CTBT IMS sites 

The infrasound team at the Geophysical Institute, UAF has been charged with the installation, testing and operation of three CTBT IMS sites.  These sites are described briefly below and detailed descriptions may be found by selecting from the list in the panel at the left.

 

Windless Bight, Antarctica

We installed a preliminary CTBT IMS site at Windless Bight, Antarctica during the 2001 austral summer.  Data from the array began to flow to our data base and to the US IDC in February, 2001.  Since then the site has returned data continuously with over 95% up-time.  The microphone array is comprised of eight microphones with five microphones in an outer, pentagonal array and three microphones centered as a triangular sub-array within the pentagon.  Currently, we are in the testing and evaluation phase of operation and we are preparing the site for certification by the CTBT.  

 

Fairbanks, Alaska

We have begun assembling the equipment that will be installed in a forested area north of the Geophysical Institute on the University of Alaska campus.  This is the same area that has been the site of the Fairbanks DOE array.  The site construction is planned to be complete by September 2002 and preliminary data flow is expected to begin at that time.

 

Palmer, Antarctica

We have completed the site survey at Palmer, Antarctica and are awaiting funds to proceed with the initial installation. The Palmer station is situated on a rocky outcrop seaward of a glacier field.  The infrasound sensors will have to be placed among the islands which make up the archipelago.  We are planning to install and eight microphone array to insure there is sufficient redundancy to allow the array to operate in the case of power outages at the remote sensor sites.

 

The Fairbanks DOE Array 

Established in 1999 under a contract with the Department of Energy, the Fairbanks array has operated continuously for over two years.  The original array was modeled after the CTBT prototype with four microphones arranged in a triangle with one microphone located near the center.  The array is scheduled for upgrade to an 8 microphone CTBT IMS site during the summer of 2002. 

The microphone enclosure shown at the left will be replaced by a CTBT-standard vault when the upgrade is completed.

 

 

 

 

Back to Top
Return to Infrasound Home Page


For problems or questions regarding this web contact John Olson at jvo@gi.alaska.edu.
Last updated: December 09, 2002.